The M21 and M31 have been completed and are expected to arrive at the factory on June 10th. However, to solve the compatibility issues with ASUS RTX4060 lp before which cause a delay in the following schedule. We will provide a USD$20 discount as compenstation.
We are working hard to ship the M21/M31 before middle of June. For the exact shipping date, we will inform you at a later time.
Shipping Status Update
The 4th week of May | The production of the case is completed |
The 1st week of June | The surface treatment of the product is completed |
The 2nd week of June | Case assembly and quality check |
The 3rd week of June | The shipments are being transported to our office |
June 21 | The shipments arrived at our office on June.21 and are expected to start shipping next Monday. |
The 4th week of June | The preorders of M31 have been shipped. |
July 1 | The preorders of M21 have been shipped. |
Late July | Due to the shipping delay, pre-order customers will receive a $20 compensation and a $10 refund due to a price reduction of the PCIe riser cable, total $30 in late July. | End of August | Due to the shipping delay, pre-order customers will receive a $20 compensation and a $10 refund due to a price reduction of the PCIe riser cable, totaling $30, but the compensation will be delayed and sent out by the end of August. |